Projects

We take projects through 4 stages: Design, Estimating/Budgeting, Execution, and Closeout. We utilize industry-leading estimating software that integrates into our project controls software so we are managing budgets and schedules from inception to closeout. We have executed projects in a variety of industries, including: power plants, oil refineries, fuel terminals, food processing, mining, pulp and paper, I&C, startup and commissioning.

↓ See our work

Shell Oil

  • Switchgear Cleaning
  • Maintenance Audit

We cleaned, tested, and inspected electrical equipment in a controlled outage of the plant. We ensured that everything was in working order for the plant, and were able to identify if we needed to make repairs on equipment that was at risk for failure. Our initial preparations allowed us to complete the necessary repairs during the first outage, saving both time and money.

Jackson Steele, CEO
Crasornare INC.

Sit amet est placerat in egestas erat imperdiet sed. Quis blandit turpis cursus in hac habitasse platea dictumst.

Page 1 Created with Sketch.

Phillips 66

  • Capital Improvement
  • PLC Upgrades

This project included the replacement of old PLC control systems, new cable and raceways, and coordination of plant wide outages to make final change overs. This project required craftsmanship, planning, and attention to detail beyond a normal construction project. We successfully executed pre-work and outage work to provide the plant with an upgraded control system while limiting down time.

Jackson Steele, CEO
Crasornare INC.

Sit amet est placerat in egestas erat imperdiet sed. Quis blandit turpis cursus in hac habitasse platea dictumst.

Page 1 Created with Sketch.

Kinder Morgan

  • Radio Installation

We installed a radio control system to enhance the customer experience for Kinder Morgan. The system gives the customer the ability to control and monitor flow of product in a process pipe that is not directly on their plant site. We worked with multiple agencies to ensure the project was completed in a timely manner and in a way that met all agencies safety protocols.

Jackson Steele, CEO
Crasornare INC.

Sit amet est placerat in egestas erat imperdiet sed. Quis blandit turpis cursus in hac habitasse platea dictumst.

Page 1 Created with Sketch.

KapStone Paper & Packaging

  • Cold Outage

This project included High Voltage Terminations, Cleaning, Testing and inspection of Medium Voltage Switchgear throughout the Plant. It required around the clock support. We completed the project on budget and ahead of schedule with zero safety issues.

Page 1 Created with Sketch.

Sonoco Energy Trust Partners

  • Butane Blending

We completed the installation of a new butane blending system. This included adding a new control building and electrical building along with associated Conduit, Tray, Cable and Control Device Installation.

Page 1 Created with Sketch.

APS - Ocotillo Plant

  • New Construction of a 550MW Natural Gas Peaking Plant

This project consisted of Instrument and Controls Startup and Commissioning support. We provided a team of Electricians and I&C Technicians to complete VLF testing on power feeders, functional testing of control systems along with troubleshooting and startup support.

Page 1 Created with Sketch.

MWH Constructors

  • 9 Plex Addition

We installed a 9 plex trailer for construction headquarters at an unnamed customers facility that specializes in the manufacturing of computer processing chips.

Page 1 Created with Sketch.

APS – Sundance Plant

  • GSU Replacement Project

We completed the demolition of an existing GSU and rewiring of a new GSU. This included the demolition of existing systems, Installation of new Power and control systems and rewiring of controls in electrical feeder cabinets.

Page 1 Created with Sketch.

APS – Redhawk Plant

  • CT Generator Protection Relays

This project consisted of cable installation during a fall outage for the addition of Protection Relays to an existing system.

Page 1 Created with Sketch.

Jones Lang Lasalle

  • VAV Upgrades

This project included the installation of new PCV’s and associated controls throughout existing conference rooms at an unnamed customers facility that specializes in the manufacturing of computer processing chips.

Page 1 Created with Sketch.

Work with us

We are committed to quality and clear communication as a foundation for successful projects.

Start here

Path Created with Sketch.

Find a career

Our people are our greatest resource, which is why we’re dedicated to training and developing each individual.

Start here